The Planning Brief | Autumn
UK Planning & Infrastructure Consenting
October 31, 2024
The Planning Brief | AutumnUK Planning & Infrastructure ConsentingOctober 31, 2024 Welcome to the second edition of The Planning Brief, a quarterly update from our UK Planning & Consenting team on key regulations and judgments in the UK.
Infrastructure Consenting – PA 2008R (on the application of Dr Andrew Boswell) v Secretary of State for Energy Security and Net Zero [2024] EWHC 2128 (Admin) The High Court dismissed an application for judicial review of the Secretary of State’s decision to grant a development consent order for the Net Zero Teesside Carbon Capture Use and Storage project (“the Project”), confirming that challenges to those decisions can only proceed on points of law. View document The Claimant in this case argued that the Secretary of State’s reasons for granting development consent lacked sound reasoning and misinterpreted the law. The Claimant argued that the Secretary of State relied on the Institute of Environmental Management and Assessment ("IEMA") Guidance which indicated significant adverse effects of Green House Gas emissions, therefore the Secretary of State’s reasons for concluding that the Project would help deliver net zero were inadequate. The High Court found that the Secretary of State’s decision letter was clear and relied on relevant policy. Justice Lieven found that the Secretary of State’s reasoning and conclusions made sense if she was assessing significance on the simple basis of EN-1 and EN-2, and through the clear approach that 20 million tonnes of CO2 was a very large quantum of greenhouse gas emissions. Her reasons also made sense if they were read in such a way that she was applying the more absolute analysis at the Environmental Impact Assessment (EIA) stage, and then weighing that against the broader policy context of transition to net zero at the substantive stage. The purpose of EIA was to improve environmental decision making, not create an obstacle course for it. Justice Lieven found that the Claimant had deliberately ignored the national policy position on the net zero trajectory and the need for both Carbon Capture Storage (CCS) and Carbon Capture Storage and Utilisation (CCSU) in making their arguments. Once again, the courts have emphasised that challenges to decisions of this nature must be founded on points of law – any attempt to collaterally challenge underlying policy will not succeed. However, the Court of Appeal has accepted the Claimant’s application to appeal the High Court’s decision. The appeal is due to be heard in March 2025. If the Court of Appeal finds merit in Dr Boswell’s arguments, it could overturn the High Court’s decision which may lead to the revocation of the project’s approval. The Court of Appeal decision is expected to have a significant impact on the interpretation of the National Policy Statement for Energy (EN-1). Lithium Mining and Processing Project in Cornwall treated as a nationally significant infrastructure project
The Secretary of State issued a direction under section 35 of the Planning Act 2008 that a proposed Lithium Mining and Processing Project in Cornwall is to be treated as a Nationally Significant Infrastructure Project and consented through the DCO regime. View document
The project aims to extract and process lithium, a critical component for batteries used in electric vehicles and renewable energy storage. It comprises:
The Secretary of State concluded that the project by itself is of national significance for the following reasons:
The project is the first of its type to be brought within the NSIP regime will be important in securing a domestic lithium supply to support the UK’s transition to renewable energy and will also help to create employment opportunities locally. It may also help to pave the way for future lithium mining projects which will help to meet the UK’s growing needs. Planning PolicyNational Planning Policy Framework Consultation closed on 24 September The Government’s consultation on its proposed reforms to the NPPF closed on 24 September 2024. View document The consultation (which affects England only) included questions relating to the assessment of housing need and delivery of affordable housing, as well as the proposed concept of the “grey belt,” principles relating to the use of brownfield and green belt land, and how green energy development can be supported. Some of the key changes include:
Vistry Homes Limited v Secretary of State for Levelling Up, Housing and Communities [2024] Green Belt development refusals upheld: the High Court dismissed appeals by Vistry Homes Limited and Fairfax Acquisitions Limited against two decisions to refuse appeals to the Secretary of State for Levelling Up, Housing and Communities for large housing schemes on Green Belt land. View document The Claimants challenged:
in weighing up the ‘Very Special Circumstances’ balance required to approve development in the Green Belt. BNG Justice Holgate found that when attributing ‘limited’ and ‘moderate’ weight to the developments’ BNG provisions, the Inspector had treated the not-yet-in-force BNG legislation as a benchmark and was entitled to do so. Previously Developed Land On the use of PDL the High Court found that policy on the development of PDL is contingent on there being no conflict with other policies in the NPPF. As such, this shouldn’t alter the conclusion if the VSC balance would otherwise weigh against the proposal. Economic Benefits As for economic benefits, the Inspector was entitled to take into account that:
Crucially, the High Court found that an Inspector can give greater weight to benefits achieved in accordance with the plan-led system, and lesser weight to those which are not. Labour GovernmentSince coming into power Labour have made clear their ambition to reform the planning and infrastructure regime. View document
It was announced in the King’s Speech that the Government would be introducing a Planning and Infrastructure Bill to accelerate the delivery of high quality planning infrastructure and housing and proposals include the following:
Environmental Impact AssessmentThe High Court has quashed the decision to grant planning permission for a new coal mine in Cumbria after upholding four of the five grounds.
Friends of the Earth and another -v- Secretary of State for Levelling Up, Housing and Communities and others [2024] EWHC 2349 (Admin) . View document The successful grounds of challenge were:
The case provides a helpful example of how the principles of the Finch case are to be applied in practice (particularly as it is one of first cases considering this issue since Finch was decided). It also provides useful clarification that full information and a separate assessment is needed from a developer seeking to demonstrate a substitution effect. Register to receive future editions of the UK Planning Brief straight to your inbox. Key contacts
Latest Insights
Latest News
Latest Events
legal updates June 02, 2026 UK Retail Finance Horizon Scanner - May 2026 legal updates June 02, 2026 Employer contributions to the Teachers' Pension Scheme (TPS) set to ease fo... legal updates June 01, 2026 UK: Reform of the Consumer Credit Act 1974 takes shape legal updates May 29, 2026 Consumer Lens - Session 1 | The Rise of European Class Actions client news June 02, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... firm news June 01, 2026 Eversheds Sutherland strengthens restructuring offering with senior partner... firm news June 01, 2026 Eversheds Sutherland strengthens Commercial Advisory practice with technolo... client news May 28, 2026 Eversheds Sutherland advises Schroders Greencoat on acquisition of Dutch bi... virtual Spanish employment law training June 02, 2026 2pm - 5pm (BST) Virtual virtual Education Webinar - Legal refresher for education institutions – governance... June 04, 2026 11:00AM - 12:00PM virtual UK employment law training June 09, 2026 1pm - 4pm (BST) Virtual virtual Education Webinar - Occupational Stress : Preventing Suffering, Enhancing W... June 10, 2026 11:00AM - 12:00PM |